Venture Global, Inc.
Close on Nov 20, 2026Market cap $29.88BP/E 9.4Yield 0.25%
Venture Global CP2 LNG Project — Site Construction Progress by Quarter
CP2 LNG Project — Site Construction Progress (%)
Venture Global CP2 LNG Project — Site Construction Progress: 36.0% in Q2 2026.
Where the Q2 2026 figure comes from
“36% Construction(1)”
Source: Venture Global Q2 2026 Investor Presentation (Aug 11, 2026) ↗
On-site construction completion for CP2 LNG in Cameron Parish, LA (Phase 1 FID July 2025; Phase 2 FID March 2026; target first LNG H2 2027)
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | CP2 LNG Project — Site Construction Progress (%) | Year on year | Source |
|---|---|---|---|---|
| Q2 2026 | Jun 30, 2026 | 36.0% | – | Venture Global Q2 2026 Investor Presentation (Aug 11, 2026) ↗ |
| Q1 2026 | Mar 31, 2026 | 27.0% | – | Venture Global Q1 2026 Investor Presentation (May 12, 2026) ↗ |
| Q4 2025 | Dec 31, 2025 | 21.0% | – | Venture Global Q4 & FY2025 Investor Presentation (Mar 2, 2026) ↗ |
Breakdown
What makes up CP2 LNG Project — Site Construction Progress
Cite this data
StockData. (2026). Venture Global CP2 LNG Project — Site Construction Progress (%), quarterly Q4 2025–Q2 2026 [Data set]. Compiled from Venture Global SEC filings and investor materials. https://stockdatahq.com/stocks/vg/kpis/cp2-epc-construction-pct
See every metric in the Venture Global KPI table. Data updated Nov 7, 2026.