Venture Global CP2 LNG Project — Site Construction Progress by Quarter

CP2 LNG Project — Site Construction Progress (%)

Venture Global CP2 LNG Project — Site Construction Progress: 36.0% in Q2 2026.

Latest, Q2 2026
36.0%
Period ended Jun 30, 2026
Change on a year earlier
–
History
3 quarters
Since Q4 2025
Sources
3
Documents cited below

Where the Q2 2026 figure comes from

“36% Construction(1)”

Source: Venture Global Q2 2026 Investor Presentation (Aug 11, 2026) ↗

On-site construction completion for CP2 LNG in Cameron Parish, LA (Phase 1 FID July 2025; Phase 2 FID March 2026; target first LNG H2 2027)

quarterly history

Hover a value to see the sentence it was read from; calculated values show their formula

PeriodEndedCP2 LNG Project — Site Construction Progress (%)Year on yearSource
Q2 2026Jun 30, 202636.0%–Venture Global Q2 2026 Investor Presentation (Aug 11, 2026) ↗
Q1 2026Mar 31, 202627.0%–Venture Global Q1 2026 Investor Presentation (May 12, 2026) ↗
Q4 2025Dec 31, 202521.0%–Venture Global Q4 & FY2025 Investor Presentation (Mar 2, 2026) ↗

Breakdown

What makes up CP2 LNG Project — Site Construction Progress

Cite this data

StockData. (2026). Venture Global CP2 LNG Project — Site Construction Progress (%), quarterly Q4 2025–Q2 2026 [Data set]. Compiled from Venture Global SEC filings and investor materials. https://stockdatahq.com/stocks/vg/kpis/cp2-epc-construction-pct

See every metric in the Venture Global KPI table. Data updated Nov 7, 2026.

See a number that looks wrong?