IREN Ltd
Close on Nov 25, 2026Market cap $5.06BP/E –Yield 0.00%
IREN Secured Grid-Connected Power Capacity: 5,000.00 MW in Q1 FY27, up 66.7% from a year earlier.
Where the Q1 FY27 figure comes from
“As of September 30, 2026, we had executed grid connection agreements, letters of agreement or equivalents representing approximately 5GW of total power capacity in the United States, Canada, Spain and Australia and data center projects in varying stages of development.”
Total grid-connected power capacity secured via executed connection agreements, letters of agreement, or equivalents across North America, Europe, and Asia Pacific (~5,000 MW / 5.0 GW at Q4 FY26 and Q1 FY27, up from 4,510 MW at Q2–Q3 FY26 and 2,910 MW at FY25). Excludes >35 GW multi-year development pipeline.
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | Secured Grid-Connected Power Capacity | Year on year | Source |
|---|---|---|---|---|
| Q1 FY27CQ3 2026 | Sep 30, 2026 | 5,000.00 | +66.7% | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
| Q4 FY26CQ2 2026 | Jun 30, 2026 | 5,000.00 | +71.8% | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
| Q3 FY26CQ1 2026 | Mar 31, 2026 | 4,510.00 | – | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
| Q2 FY26CQ4 2025 | Dec 31, 2025 | 4,510.00 | – | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
| Q1 FY26CQ3 2025 | Sep 30, 2025 | 3,000.00 | – | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
| Q4 FY25CQ2 2025 | Jun 30, 2025 | 2,910.00 | – | IREN Investor Relations — https://www.sec.gov/Archives/edgar/data/1878848/000162828024038677/iren-20240630.htm ↗ |
Breakdown
What makes up secured Grid-Connected Power Capacity
- Childress Campus (Texas, USA)750.00 · Q1 FY27
- Sweetwater 1 Campus (Texas, USA)1,400.00 · Q1 FY27
- Sweetwater 2 Campus (Texas, USA)600.00 · Q1 FY27
- Kiowa Campus (Oklahoma, USA)1,600.00 · Q1 FY27
- Mackenzie Campus (British Columbia, Canada)100.00 · Q1 FY27
- Prince George Campus (British Columbia, Canada)50.00 · Q1 FY27
- Canal Flats Campus (British Columbia, Canada)30.00 · Q1 FY27
Cite this data
StockData. (2026). IREN Secured Grid-Connected Power Capacity, quarterly Q4 FY25–Q1 FY27 [Data set]. Compiled from IREN SEC filings and investor materials. https://stockdatahq.com/stocks/iren/kpis/dc-secured-power-mw
See every metric in the IREN KPI table. Data updated Nov 8, 2026.
See a number that looks wrong?