IREN Ltd
Close on Nov 24, 2026Market cap $5.10BP/E –Yield 0.00%
IREN Capital Commitments by Year
Capital Commitments — Total Contractual Obligations
IREN Capital Commitments: $13,810M in FY2026, up 3,644.6% from a year earlier.
Where the FY2026 figure comes from
Source: SEC Form 10-Q (filed 2026-11-05) ↗
Total contractual capital commitments for GPU purchases, data center construction (Horizons 1–6 at Childress, Sweetwater 1 & 2, and British Columbia liquid/air-cooled retrofits), and electrical equipment ($9,927.0M at Q1 FY27, up from $7,056.0M at Q4 FY26 and $291.7M at Q4 FY25).
annual history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | Capital Commitments — Total Contractual Obligations | Year on year | Source |
|---|---|---|---|---|
| FY2026CY2026 | Jun 30, 2026 | 13,810.00 | +3,644.6% | SEC Form 10-Q (filed 2026-11-05) ↗ |
| FY2025CY2025 | Jun 30, 2025 | 368.80 | +89.5% | SEC Form 10-K (filed 2026-08-27) ↗ |
| FY2024CY2024 | Jun 30, 2024 | 194.60 | +2,494.7% | SEC Form 10-K (filed 2025-08-28) ↗ |
| FY2023CY2023 | Jun 30, 2023 | 7.50 | -97.8% | SEC Form 6-K (filed 2024-05-15) ↗ |
| FY2022CY2022 | Jun 30, 2022 | 346.60 | +121.3% | SEC Form 20-F (filed 2023-09-13) ↗ |
| FY2021CY2021 | Jun 30, 2021 | 156.60 | – | SEC Form 20-F (filed 2022-09-13) ↗ |
Breakdown
What makes up capital Commitments
- Mining & GPU Hardware Prepayments and Deposits (Noncurrent)107.00 · FY2026
- Accrued Capital Expenditures in Accounts Payable & Accrued Expenses–
- Capital Commitments Due Within 1 Year — Mining Hardware (Legacy Breakdown)117.00 · FY2024
- Capital Commitments Due Within 1 Year — Data Center & Other (Legacy Breakdown)77.70 · FY2024
Cite this data
StockData. (2026). IREN Capital Commitments, annual FY2021–FY2026 [Data set]. Compiled from IREN SEC filings and investor materials. https://stockdatahq.com/stocks/iren/kpis/capex-commitments-total
See every metric in the IREN KPI table. Data updated Nov 8, 2026.
See a number that looks wrong?