$47.36−0.18 (-0.38%)

Close on Nov 24, 2026Market cap $27.42BP/E 22.8Yield 3.72%

FirstEnergy FirstEnergy Long-Term Total Data Center Demand by Quarter

FirstEnergy Long-Term Total Data Center Demand — Contracted + Pipeline Through 2035/2036 (MW)

FirstEnergy FirstEnergy Long-Term Total Data Center Demand: 26,950.00 mw in Q3 2026, up 74.4% from a year earlier.

Latest, Q3 2026
26,950.00
Period ended Sep 30, 2026
Change on a year earlier
+74.4%
15,450.00 in Q3 2025
History
5 quarters
Since Q3 2025
Sources
5
Documents cited below

Where the Q3 2026 figure comes from

“FE Contracted 2,190 6,730 7,880 Pipeline - 6,390 19,070 Total 2,190 13,120 26,950”

Source: FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q3 (filed 2026-10-27, 0001031296-26-000142) ↗

Total long-term data center load demand (Contracted + Pipeline MW) across FirstEnergy's five-state transmission and distribution footprint, reaching 16,695 MW (3,885 MW Contracted + 12,810 MW Pipeline) in Q3 2026 alongside 117 GW of active large-load studies (>500 MW).

quarterly history

Hover a value to see the sentence it was read from; calculated values show their formula

Breakdown

What makes up firstEnergy Long-Term Total Data Center Demand

Cite this data

StockData. (2026). FirstEnergy FirstEnergy Long-Term Total Data Center Demand, quarterly Q3 2025–Q3 2026 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/dc-lt-total-mw-total

See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.

See a number that looks wrong?