FirstEnergy Corp
Close on Nov 24, 2026Market cap $27.42BP/E 22.8Yield 3.72%
FirstEnergy FirstEnergy Long-Term Total Data Center Demand by Quarter
FirstEnergy Long-Term Total Data Center Demand — Contracted + Pipeline Through 2035/2036 (MW)
FirstEnergy FirstEnergy Long-Term Total Data Center Demand: 26,950.00 mw in Q3 2026, up 74.4% from a year earlier.
Where the Q3 2026 figure comes from
“FE Contracted 2,190 6,730 7,880 Pipeline - 6,390 19,070 Total 2,190 13,120 26,950”
Total long-term data center load demand (Contracted + Pipeline MW) across FirstEnergy's five-state transmission and distribution footprint, reaching 16,695 MW (3,885 MW Contracted + 12,810 MW Pipeline) in Q3 2026 alongside 117 GW of active large-load studies (>500 MW).
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | FirstEnergy Long-Term Total Data Center Demand — Contracted + Pipeline Through 2035/2036 (MW) | Year on year | Source |
|---|---|---|---|---|
| Q3 2026 | Sep 30, 2026 | 26,950.00 | +74.4% | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q3 (filed 2026-10-27, 0001031296-26-000142) ↗ |
| Q2 2026 | Jun 30, 2026 | 24,785.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q2 (filed 2026-07-28, 0001031296-26-000122) ↗ |
| Q1 2026 | Mar 31, 2026 | 19,120.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q1 (filed 2026-04-28, 0001031296-26-000084) ↗ |
| Q4 2025 | Dec 31, 2025 | 16,985.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2025Q4 (filed 2026-02-17, 0001031296-26-000041) ↗ |
| Q3 2025 | Sep 30, 2025 | 15,450.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2025Q3 (filed 2025-10-22, 0001031296-25-000080) ↗ |
Breakdown
What makes up firstEnergy Long-Term Total Data Center Demand
- Long-Term Contracted Data Center Load — FE Total (MW)7,880.00 · Q3 2026
- Long-Term Pipeline Data Center Load — FE Total (MW)19,070.00 · Q3 2026
- Cumulative Large-Load Studies >500 MW Submitted — FE Total (GW)117.00 · Q3 2026
- Active Near-Term (2026) Contracted Data Center Load — FE Total (MW)2,190.00 · Q3 2026
- 5-Year Horizon (Through 2030/2031) Total Data Center Demand — FE Total (MW)13,120.00 · Q3 2026
- 5-Year Horizon Contracted Data Center Load — FE Total (MW)6,730.00 · Q3 2026
- 5-Year Horizon Pipeline Data Center Load — FE Total (MW)6,390.00 · Q3 2026
Cite this data
StockData. (2026). FirstEnergy FirstEnergy Long-Term Total Data Center Demand, quarterly Q3 2025–Q3 2026 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/dc-lt-total-mw-total
See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.
See a number that looks wrong?