StockData
FirstEnergy Corp logo

FirstEnergy Corp

FENYSEElectric ServicesFiscal year ends December 31
Financials through Q3 FY2026, quarter ended Sep 30, 2026Last filing: 10-Q on Oct 28, 2026Score 7/3043% above fair value
$47.36−0.18 (-0.38%)

Close on Nov 24, 2026Market cap $27.42BP/E 22.8Yield 3.72%

FirstEnergy Long-Term Pipeline Data Center Load by Quarter

Long-Term Pipeline Data Center Load — FE Total (MW)

FirstEnergy Long-Term Pipeline Data Center Load: 19,070.00 mw in Q3 2026, up 63.3% from a year earlier.

Latest, Q3 2026
19,070.00
Period ended Sep 30, 2026
Change on a year earlier
+63.3%
11,675.00 in Q3 2025
History
6 quarters
Since Q2 2025
Sources
6
Documents cited below

Where the Q3 2026 figure comes from

“FE Contracted 2,190 6,730 7,880 Pipeline - 6,390 19,070 Total 2,190 13,120 26,950”

Source: FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q3 (filed 2026-10-27, 0001031296-26-000142) ↗

Reported in FirstEnergy Form 8-K Strategic & Financial Highlights Slide Decks (Data Center Demand & Pipeline).

quarterly history

Hover a value to see the sentence it was read from; calculated values show their formula

Cite this data

StockData. (2026). FirstEnergy Long-Term Pipeline Data Center Load, quarterly Q2 2025–Q3 2026 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/dc-lt-pipeline-mw-total

See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.

See a number that looks wrong?