Dominion Energy, Inc
Close on Nov 20, 2026Market cap $58.30BP/E 22.0Yield 4.03%
Dominion Energy Coastal Virginia Offshore Wind (2.6 GW CVOW) by Quarter
Coastal Virginia Offshore Wind (2.6 GW CVOW) — Project Completion
Dominion Energy Coastal Virginia Offshore Wind (2.6 GW CVOW): 85.0% in Q3 2026, up 19.0 pts from a year earlier.
Where the Q3 2026 figure comes from
“Significant progress reduces project risk: ~85% complete (updated)”
Source: Dominion Energy 2026Q3 Earnings Call Slide Presentation ↗
Construction completion percentage of the 2.6 GW (176-turbine) regulated offshore wind project 27 miles off Virginia Beach.
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | Coastal Virginia Offshore Wind (2.6 GW CVOW) — Project Completion | Year on year | Source |
|---|---|---|---|---|
| Q3 2026 | Sep 30, 2026 | 85.00 | +19.0 pts | Dominion Energy 2026Q3 Earnings Call Slide Presentation ↗ |
| Q2 2026 | Jun 30, 2026 | 81.00 | +21.0 pts | Dominion Energy 2026Q2 Earnings Call Slide Presentation ↗ |
| Q1 2026 | Mar 31, 2026 | 75.00 | +20.0 pts | Dominion Energy 2026Q1 Earnings Call Slide Presentation ↗ |
| Q3 2025 | Sep 30, 2025 | 66.00 | – | Dominion Energy 2025Q3 Earnings Call Slide Presentation ↗ |
| Q2 2025 | Jun 30, 2025 | 60.00 | – | Dominion Energy 2025Q2 Earnings Call Slide Presentation ↗ |
| Q1 2025 | Mar 31, 2025 | 55.00 | – | Dominion Energy 2025Q1 Earnings Call Slide Presentation ↗ |
| Q4 2024 | Dec 31, 2024 | 50.00 | – | Dominion Energy 2024Q4 Earnings Call Slide Presentation ↗ |
Breakdown
What makes up coastal Virginia Offshore Wind (2.6 GW CVOW)
- CVOW Monopiles / Turbines Installed Milestone Count44.00 · Q3 2026
- CVOW Turbines Remaining to Install132.00 · Q3 2026
- CVOW Project-to-Date Capital Invested10.10 · Q3 2026
- CVOW Total Estimated Project Capital Budget11.70 · Q3 2026
- CVOW Remaining Capital Cost to Complete1.50 · Q3 2026
- CVOW Unallocated Contingency Reserve123.00 · Q3 2026
- Stonepeak 50% Noncontrolling Partner Capital Contributions (CVOW)–
- CVOW Expected Levelized Cost of Energy (LCOE — incl. RECs)62.00 · Q3 2026
- CVOW Expected Levelized Cost of Energy (LCOE — excl. RECs)100.00 · Q3 2026
Cite this data
StockData. (2026). Dominion Energy Coastal Virginia Offshore Wind (2.6 GW CVOW), quarterly Q4 2024–Q3 2026 [Data set]. Compiled from Dominion Energy SEC filings and investor materials. https://stockdatahq.com/stocks/d/kpis/cvow-pct-complete
See every metric in the Dominion Energy KPI table. Data updated Nov 6, 2026.
See a number that looks wrong?