Dominion Energy CVOW Total Estimated Project Capital Budget by Quarter

Dominion Energy CVOW Total Estimated Project Capital Budget: $11.70B in Q3 2026, up 4.5% from a year earlier.

Latest, Q3 2026
11.70
Period ended Sep 30, 2026
Change on a year earlier
+4.5%
11.20 in Q3 2025
History
7 quarters
Since Q1 2025
Sources
7
Documents cited below

Where the Q3 2026 figure comes from

“▪ Current capital budget: $11.65B including contingency (no change)”

Source: Dominion Energy 2026Q3 Earnings Call Slide Presentation ↗

Reported in Earnings Call Slide Presentations & Form 10-Q.

quarterly history

Hover a value to see the sentence it was read from; calculated values show their formula

Cite this data

StockData. (2026). Dominion Energy CVOW Total Estimated Project Capital Budget, quarterly Q1 2025–Q3 2026 [Data set]. Compiled from Dominion Energy SEC filings and investor materials. https://stockdatahq.com/stocks/d/kpis/cvow-cap-budget-b

See every metric in the Dominion Energy KPI table. Data updated Nov 6, 2026.