CoreWeave Capitalized Interest Cost by Quarter
Capitalized Interest Cost (Data Centers & GPU Clusters Under Construction) ($M)
CoreWeave Capitalized Interest Cost: $79M in Q2 2026, up 243.5% from a year earlier.
Where the Q2 2026 figure comes from
Source: SEC Form 10-Q (filed 2026-08-12) ↗
Interest cost capitalized into Construction in Progress during active buildout ($89.0M in Q2 2026 vs. $63.0M in Q1 2026, $134.0M in FY2025, and $66.0M in FY2024).
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | Capitalized Interest Cost (Data Centers & GPU Clusters Under Construction) ($M) | Year on year | Source |
|---|---|---|---|---|
| Q2 2026 | Jun 30, 2026 | 79 | +243.5% | SEC Form 10-Q (filed 2026-08-12) ↗ |
| Q1 2026 | Mar 31, 2026 | 97 | +646.2% | SEC Form 10-Q (filed 2026-05-08) ↗ |
| Q4 2025 | Dec 31, 2025 | 84 | +64.7% | SEC Form 10-K (filed 2026-03-02) ↗ |
| Q3 2025 | Sep 30, 2025 | 61.8 | +76.1% | SEC Form 10-Q (filed 2025-11-13) ↗ |
| Q2 2025 | Jun 30, 2025 | 23 | -43.5% | SEC Form 10-Q (filed 2026-08-12) ↗ |
| Q1 2025 | Mar 31, 2025 | 13 | -59.6% | SEC Form 10-Q (filed 2026-05-08) ↗ |
| Q4 2024 | Dec 31, 2024 | 51 | – | SEC Form 10-K (filed 2026-03-02) ↗ |
| Q3 2024 | Sep 30, 2024 | 35.1 | – | SEC Form 10-Q (filed 2025-11-13) ↗ |
| Q2 2024 | Jun 30, 2024 | 40.7 | – | SEC Form 10-Q (filed 2025-08-13) ↗ |
| Q1 2024 | Mar 31, 2024 | 32.2 | – | SEC Form 10-Q (filed 2025-05-15) ↗ |
Cite this data
StockData. (2026). CoreWeave Capitalized Interest Cost ($M), quarterly Q1 2024–Q2 2026 [Data set]. Compiled from CoreWeave SEC filings and investor materials. https://stockdatahq.com/stocks/crwv/kpis/interest-capitalized
See every metric in the CoreWeave KPI table. Data updated Nov 3, 2026.
See a number that looks wrong?