StockData
NextEra Energy Inc logo

NextEra Energy Inc

NEENYSEElectric ServicesFiscal year ends December 31Also trades as NEE.PN, NEE.PS, NEE.PT, NEE.PU, NEE.PV, NEE.PW
Financials through Q3 FY2026, quarter ended Sep 30, 2026Last filing: 10-Q on Oct 21, 2026Score 14/308% below fair value
$85.41+0.83 (+0.98%)

Close on Nov 25, 2026Market cap $179.13BP/E 15.4Yield 2.66%

NextEra Energy FPL Transmission & Distribution Network Circuit Miles by Year

NextEra Energy FPL Transmission & Distribution Network Circuit Miles: 93,000 in FY2025, up 2.2% from a year earlier.

Latest, FY2025
93,000
Period ended Dec 31, 2025
Change on a year earlier
+2.2%
91,000 in FY2024
History
5 years
Since FY2020
Sources
5
Documents cited below

Where the FY2025 figure comes from

“As of December 31, 2025, FPL had 35,963 MW of net generating capacity, approximately 93,000 circuit miles of transmission and distribution lines and 932 substations”

Source: NextEra Energy / FPL 10-K (10k_2025, filed 2026-02-13, 0000753308-26-000015) ↗

Includes overhead and underground distribution & high-voltage transmission lines across Florida (~93,000 circuit miles at FY2025).

annual history

Hover a value to see the sentence it was read from; calculated values show their formula

Breakdown

What makes up FPL Transmission & Distribution Network Circuit Miles

Cite this data

StockData. (2026). NextEra Energy FPL Transmission & Distribution Network Circuit Miles, annual FY2020–FY2025 [Data set]. Compiled from NextEra Energy SEC filings and investor materials. https://stockdatahq.com/stocks/nee/kpis/fpl-td-circuit-miles

See every metric in the NextEra Energy KPI table. Data updated Oct 31, 2026.

See a number that looks wrong?