FirstEnergy Corp
Close on Nov 24, 2026Market cap $27.42BP/E 22.8Yield 3.72%
FirstEnergy Maryland (Potomac Edison / TrAILCo) by Quarter
Maryland (Potomac Edison / TrAILCo) — Active Near-Term (2026) Contracted Data Center Load (MW)
FirstEnergy Maryland (Potomac Edison / TrAILCo): 825.00 mw in Q3 2026.
Where the Q3 2026 figure comes from
“MD Contracted 825 2,045 3,045 Pipeline - 670 1,585 Total 825 2,715 4,630”
Reported in FirstEnergy Form 8-K Strategic & Financial Highlights Slide Decks (Data Center Demand & Pipeline).
quarterly history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | Maryland (Potomac Edison / TrAILCo) — Active Near-Term (2026) Contracted Data Center Load (MW) | Year on year | Source |
|---|---|---|---|---|
| Q3 2026 | Sep 30, 2026 | 825.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q3 (filed 2026-10-27, 0001031296-26-000142) ↗ |
| Q2 2026 | Jun 30, 2026 | 825.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q2 (filed 2026-07-28, 0001031296-26-000122) ↗ |
| Q1 2026 | Mar 31, 2026 | 825.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2026Q1 (filed 2026-04-28, 0001031296-26-000084) ↗ |
| Q4 2025 | Dec 31, 2025 | 825.00 | – | FirstEnergy Form 8-K Strategic & Financial Highlights 2025Q4 (filed 2026-02-17, 0001031296-26-000041) ↗ |
Cite this data
StockData. (2026). FirstEnergy Maryland (Potomac Edison / TrAILCo), quarterly Q4 2025–Q3 2026 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/dc-active-contracted-mw-md
See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.
See a number that looks wrong?