FirstEnergy FirstEnergy Total Owned & Controlled Generating Capacity by Year
FirstEnergy Total Owned & Controlled Generating Capacity (MW, Form 10-K Item 2)
FirstEnergy FirstEnergy Total Owned & Controlled Generating Capacity: 3,677.00 mw in FY2025, up 0.2% from a year earlier.
Where the FY2025 figure comes from
“|| Total | 3,677 | 67 | 3,610 | 18,028 | 336 | 17,692”
Source: FirstEnergy Form 10-K FY2025 (filed 2026-02-18, 0001031296-26-000046) ↗
Year-end owned and contractually controlled generating capacity across Monongahela Power, Allegheny Generating Company, and OVEC (3,680 MW at YE 2025).
annual history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | FirstEnergy Total Owned & Controlled Generating Capacity (MW, Form 10-K Item 2) | Year on year | Source |
|---|---|---|---|---|
| FY2025 | Dec 31, 2025 | 3,677.00 | +0.2% | FirstEnergy Form 10-K FY2025 (filed 2026-02-18, 0001031296-26-000046) ↗ |
| FY2024 | Dec 31, 2024 | 3,671.00 | +0.7% | FirstEnergy Form 10-K FY2024 (filed 2025-02-27, 0001031296-25-000006) ↗ |
| FY2023 | Dec 31, 2023 | 3,647.00 | 0.0% | FirstEnergy Form 10-K FY2023 (filed 2024-02-13, 0001031296-24-000008) ↗ |
| FY2022 | Dec 31, 2022 | 3,647.00 | 0.0% | FirstEnergy Form 10-K FY2022 (filed 2023-02-13, 0001031296-23-000014) ↗ |
| FY2021 | Dec 31, 2021 | 3,647.00 | -5.4% | FirstEnergy Form 10-K FY2021 (filed 2022-02-16, 0001031296-22-000013) ↗ |
| FY2020 | Dec 31, 2020 | 3,857.00 | -25.2% | FirstEnergy Form 10-K FY2020 (filed 2021-02-18, 0001031296-21-000020) ↗ |
| FY2019 | Dec 31, 2019 | 5,157.00 | – | FirstEnergy Form 10-K FY2019 (filed 2020-02-10, 0001031296-20-000008) ↗ |
Breakdown
What makes up firstEnergy Total Owned & Controlled Generating Capacity
- Harrison Power Station — Haywood, WV (100% Mon Power Supercritical Coal, 3 Units, MW)1,984.00 · FY2025
- Fort Martin Power Station — Maidsville, WV (100% Mon Power Supercritical Coal, 2 Units, MW)1,098.00 · FY2025
- Bath County Pumped Storage Station — Warm Springs, VA (16.25% AGC Ownership Share, 6 Units, MW)487.00 · FY2025
- Ohio Valley Electric Corporation — OVEC (4.85% Entitlement Share, 11 Units, MW)78.00 · FY2025
- Fort Martin Solar Facility — Maidsville, WV (100% Mon Power Solar PV, MW)19.00 · FY2025
- Rivesville Solar Facility — Rivesville, WV (100% Mon Power Solar PV, MW)5.00 · FY2025
- Owned Regulated Coal-Fired Nameplate Capacity — EESG Data Tables (MW)3,082.00 · FY2025
- Owned Regulated Utility-Scale Solar PV Capacity — EESG Data Tables (MW)30.00 · FY2025
- Integrated Segment Total Generating Capacity (MW, XBRL)3,610.00 · FY2025
Cite this data
StockData. (2026). FirstEnergy FirstEnergy Total Owned & Controlled Generating Capacity, annual FY2019–FY2025 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/gen-cap-mw-total-controlled
See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.