FirstEnergy Corp
Close on Nov 20, 2026Market cap $27.23BP/E 22.6Yield 3.74%
FirstEnergy FirstEnergy Total Electric Distribution Line Miles by Year
FirstEnergy Total Electric Distribution Line Miles (Miles, Form 10-K Item 2)
FirstEnergy FirstEnergy Total Electric Distribution Line Miles: 252,959 in FY2025, up 0.3% from a year earlier.
Where the FY2025 figure comes from
“|| Total | 252,959 | 24,157”
Source: FirstEnergy Form 10-K FY2025 (filed 2026-02-18, 0001031296-26-000046) ↗
Overhead Pole Line and Underground Conduit/Cable distribution and transmission miles by operating subsidiary from Form 10-K Item 2 (200,829 distribution line miles and 24,157 transmission line miles at YE 2025).
annual history
Hover a value to see the sentence it was read from; calculated values show their formula
| Period | Ended | FirstEnergy Total Electric Distribution Line Miles (Miles, Form 10-K Item 2) | Year on year | Source |
|---|---|---|---|---|
| FY2025 | Dec 31, 2025 | 252,959 | +0.3% | FirstEnergy Form 10-K FY2025 (filed 2026-02-18, 0001031296-26-000046) ↗ |
| FY2024 | Dec 31, 2024 | 252,244 | -8.5% | FirstEnergy Form 10-K FY2024 (filed 2025-02-27, 0001031296-25-000006) ↗ |
| FY2023 | Dec 31, 2023 | 275,760 | +0.5% | FirstEnergy Form 10-K FY2023 (filed 2024-02-13, 0001031296-24-000008) ↗ |
| FY2022 | Dec 31, 2022 | 274,518 | +0.4% | FirstEnergy Form 10-K FY2022 (filed 2023-02-13, 0001031296-23-000014) ↗ |
| FY2021 | Dec 31, 2021 | 273,295 | – | FirstEnergy Form 10-K FY2021 (filed 2022-02-16, 0001031296-22-000013) ↗ |
Breakdown
What makes up firstEnergy Total Electric Distribution Line Miles
- FirstEnergy Total Electric Transmission Line Miles — 34.5 kV to 500 kV (Miles, Form 10-K Item 2)24,157 · FY2025
- Total Distribution Circuit Miles — EESG Data Tables (Circuit Miles)252,959 · FY2025
- Total Transmission Circuit Miles — EESG Data Tables (Circuit Miles)24,157 · FY2025
- FirstEnergy Pennsylvania Electric Company (FE PA) Distribution Line Miles (Miles)82,638 · FY2025
- FirstEnergy Pennsylvania Electric Company (FE PA) Transmission Line Miles (Miles)2,624 · FY2025
- Ohio Edison (OE) Distribution Line Miles (Miles)54,882 · FY2025
- Cleveland Electric Illuminating (CEI) Distribution Line Miles (Miles)31,876 · FY2025
- Toledo Edison (TE) Distribution Line Miles (Miles)15,118 · FY2025
- Jersey Central Power & Light (JCP&L) Distribution Line Miles (Miles)24,892 · FY2025
- Jersey Central Power & Light (JCP&L) Transmission Line Miles (Miles)2,620 · FY2025
- Monongahela Power (MP) Distribution Line Miles (Miles)23,166 · FY2025
- Monongahela Power (MP) Transmission Line Miles (Miles)2,612 · FY2025
- Potomac Edison (PE) Distribution Line Miles (Miles)20,387 · FY2025
- Potomac Edison (PE) Transmission Line Miles (Miles)2,092 · FY2025
- American Transmission Systems, Inc. (ATSI) Transmission Line Miles (Miles)7,965 · FY2025
- Mid-Atlantic Interstate Transmission (MAIT) Transmission Line Miles (Miles)4,281 · FY2025
- Trans-Allegheny Interstate Line (TrAILCo) Transmission Line Miles (Miles)269 · FY2025
- Keystone Appalachian Transmission (KATCo) Transmission Line Miles (Miles)1,694 · FY2025
- Smart Meter Penetration Across Retail Customer Base (%)69.0% · FY2025
- Annual Customer Energy Efficiency Program Savings (MWh)879,345.00 · FY2025
- Annual Customer Energy Efficiency Program Investment ($M)293 · FY2025
Cite this data
StockData. (2026). FirstEnergy FirstEnergy Total Electric Distribution Line Miles, annual FY2021–FY2025 [Data set]. Compiled from FirstEnergy SEC filings and investor materials. https://stockdatahq.com/stocks/fe/kpis/dx-miles-total
See every metric in the FirstEnergy KPI table. Data updated Nov 10, 2026.
See a number that looks wrong?